Chen
Chen GongEngineering project manager

Aurora New Energy Charging Station Electrical Installation

In progress

PRJ-2026-003 · Zhejiang · Ningbo

Contracting client
Aurora New Energy Technology Company
Taking over the team
Hengtong installation team
Project leader
Gao Min
Contract amount
¥980,000
Start date
2026-04-02
Planned completion
2026-06-30
Project address
Ningbo Yinzhou District Smart Industrial Park
Current progress
45%

Project Milestones

  1. Site surveyComplete 2026-04-02
  2. Quote confirmationComplete 2026-04-19
  3. Entering the market to explainComplete 2026-05-07
  4. Main constructionPlan 2026-05-25
  5. Completion acceptancePlan 2026-06-12
  6. Settlement and invoicingPlan 2026-06-30

Construction schedule

Weekly view · Progress filling

Task
3/30
4/6
4/13
4/20
4/27
5/4
5/11
5/18
5/25
6/1
6/8
6/15
6/22
6/29
Site survey
100%
Quote confirmation
100%
Entering the market to explain
100%
Main construction
45%
Completion acceptance

Project news

  1. NoteRecorded a grounding issue in the distribution box for remediation

    2026-06-03 10:05 · Gao Min