Yunqi Data Center Mechanical and Electrical Installation Project

In progress

PRJ-2026-001 · Zhejiang · Hangzhou

Contracting client
Yunqi Technology Co., Ltd.
Taking over the team
Hongji electromechanical team
Project leader
Chen Gong
Contract amount
¥2,860,000
Start date
2026-03-10
Planned completion
2026-07-20
Project address
No. 18, Yunqi Town, Yuhang District, Hangzhou City
Current progress
62%

Project Milestones

  1. Site surveyComplete 2026-03-10
  2. Quote confirmationComplete 2026-04-05
  3. Entering the market to explainComplete 2026-05-01
  4. Main constructionPlan 2026-05-28
  5. Completion acceptancePlan 2026-06-23
  6. Settlement and invoicingPlan 2026-07-20

Construction schedule

Weekly view · Progress filling

Task
3/7
3/9
3/16
3/23
3/30
4/6
4/13
4/20
4/27
5/4
5/11
5/18
5/25
6/1
6/8
6/15
6/22
6/29
7/6
7/13
7/20
Early stage
Site survey
Deepen design and quote
100%
construction
Bridge and pipeline laying
100%
Equipment installed in place
55%
System debugging
Finishing
Completion acceptance and settlement

Project news

  1. PhotoUploaded 3 photos of the chiller-room piping installation

    2026-06-03 14:20 · Hongji electromechanical team
  2. MilestoneCable tray installation completed; equipment placement is next

    2026-06-01 09:10 · Chen Gong
  3. PaymentReceived the second progress payment of ¥858,000

    2026-05-20 16:40 · Finance
  4. InvoiceIssued VAT special invoice INV-2026-002

    2026-05-06 11:00 · Finance
  5. QuoteClient accepted quote QT-2026-001

    2026-03-12 10:30 · Chen Gong