Contracting client
Yunqi Technology Co., Ltd.
Taking over the team
Hongji electromechanical team
Project leader
Chen Gong
Contract amount
¥2,860,000
Start date
2026-03-10
Planned completion
2026-07-20
Project address
No. 18, Yunqi Town, Yuhang District, Hangzhou City
Current progress
62%
Project Milestones
- Site surveyComplete 2026-03-10
- Quote confirmationComplete 2026-04-05
- Entering the market to explainComplete 2026-05-01
- Main constructionPlan 2026-05-28
- Completion acceptancePlan 2026-06-23
- Settlement and invoicingPlan 2026-07-20
Construction schedule
Weekly view · Progress filling
Project news
PhotoUploaded 3 photos of the chiller-room piping installation
2026-06-03 14:20 · Hongji electromechanical teamMilestoneCable tray installation completed; equipment placement is next
2026-06-01 09:10 · Chen GongPaymentReceived the second progress payment of ¥858,000
2026-05-20 16:40 · FinanceInvoiceIssued VAT special invoice INV-2026-002
2026-05-06 11:00 · FinanceQuoteClient accepted quote QT-2026-001
2026-03-12 10:30 · Chen Gong